Red tape delays Braddock dam project

(The Center Square) — A redundant permitting process, delays, and problems with getting plugged into the grid means headaches are routine for new power projects. For one renewable hydroelectric plant, the process has driven up the cost of the project by 30% — if not more.

A plan to build seven turbine-generators at the Braddock Locks and Dam outside Pittsburgh to produce 5.25 megawatts of electricity, as The Center Square previously reported, has had years of delays. State officials have noted that the delays have run up the cost of the project “substantially.”

However, the final cost of those delays and permitting issues is not yet known by Hydro Green Energy, the company behind the project and a number of other dam projects in the commonwealth. The delays in the process, and final approval, are too unpredictable.

“The last cost estimate we did was in 2019, and I think our cost was up 25% to 30% at that point,” Hydro Green Energy President and CEO Wayne Krouse told The Center Square.

While the permitting process can be duplicative at the federal level — in this instance, with the Army Corps of Engineers and the Federal Energy Regulatory Commission — permits aren’t the only hurdle.

- Advertisement -

“The two big issues in the renewable world in the U.S. — one is transmission. Big projects need to get their resources are in places that are not population centers, you gotta move the electrons you generate from generation point to the consumption point, to the cities,” Krouse said. “Getting new transmission is very difficult.”

Building transmission lines in America has been compared to herding cats: regulators, utility companies, property owners, and others get involved in the process, which can drag on for years. The longer the process lasts, the more uncertain the profitability of a project can become.

“The other issue is getting interconnected, and when you have big, big interconnection areas like PJM, you can have tens of thousands, close to hundreds of thousands of projects that represent a huge amount of hypothetical capacity — but how much of it is real is a question,” Krouse said.

PJM is the regional transmission organization that serves a dozen states, including Pennsylvania, that coordinates the electricity wholesale market. Electricity projects need to get plugged into PJM’s grid to transmit the power they generate.

Until a project gets interconnected, the project’s cost is still an open question.

“The problem is PJM. There’s really no point to do pricing again until PJM is ready to interconnect you. Any pricing a general contractor would give you today will not be valid in the future if it’s more than 90 days,” Krouse said. “You can’t build it unless you have your interconnection agreement completed.”

- Advertisement -

The years-long delays are a problem that PJM itself recognizes. At the end of 2022, FERC approved PJM’s reform plan to speed up interconnection approvals and clear out its request backlog. The new process would move quicker to approve projects that are “ready to go” instead of its old process of “first-come, first-served” when processing applications.

If successful, the changes could shave years off project timelines, but that kind of success remains to be seen.

The complexity of power generation projects, too, can mean a speedrun isn’t possible. The studies required by state and federal law to assess the impact of projects on people, nature, and economy serve a purpose.

“I don’t see how you interconnect to a large, interconnected system — serving tens if not 100 million people, across a very, very large geographic area — and do it in a way to make sure you’re gonna keep reliability and safety where it is, without doing these kinds of studies and taking the time to do it right,” Krouse said.

Other problems that could kill a project are out of the hands of power companies and federal regulators. Instead, the problem is local.

“It’s very hard to get it done because you get a lot of lawsuits, a lot of ‘not in my backyard,’ a lot of neighbors and residents nearby saying ‘don’t build that near me,’” Krouse said. “For some developers, it can take so long, they just quit.”

spot_img
spot_img

Hot this week

Health care company agrees to pay $22.5 million to settle claims of over billing

A health care company agreed to pay nearly $22.5...

Business association ‘disappointed’ by WA L&I’s proposed workers comp rate hike

(The Center Square) – The Association of Washington Business...

Sports betting expert offers advice on paying taxes for gambling winnings

(The Center Square) – Tax season is underway, and...

African and Caribbean Nations Call for Reparations for Slave Trade, Propose Global Fund

Nations across Africa and the Caribbean, deeply impacted by...

Sports betting bill still alive in Georgia House

(The Center Square) – A bill that would allow...

Skin Deep: How Melanin Impacts Your Body’s Response To Drugs

Scientific research is becoming more inclusive, but one area...

Educator calls for greater Black representation in tech at CES 2026

LAS VEGAS — Walking the sprawling halls of CES...

Operation Salvo launched in New York targets dozens of Trinitarios gang members

(The Center Square) – A multiagency law enforcement operation,...

Assaults against ICE up 1300%, vehicular attacks up 3200%, death threats up 8000%

Assaults against U.S. Immigration and Customs Enforcement officers are...

Does Birth Control Cause PCOS? Facts And Misconceptions Of The Disorder

Polycystic ovarian syndrome affects at least one in ten...

Texans, Americans encouraged to participate in ‘Valetine’s for Veterans’ program

(The Center Square) – Texans and Americans are encouraged...

Five battleground governor’s races for 2026

(The Center Square) - Voters from 36 states across...

More like this
Related

Skin Deep: How Melanin Impacts Your Body’s Response To Drugs

Scientific research is becoming more inclusive, but one area...

Educator calls for greater Black representation in tech at CES 2026

LAS VEGAS — Walking the sprawling halls of CES...

Operation Salvo launched in New York targets dozens of Trinitarios gang members

(The Center Square) – A multiagency law enforcement operation,...

Assaults against ICE up 1300%, vehicular attacks up 3200%, death threats up 8000%

Assaults against U.S. Immigration and Customs Enforcement officers are...