spot_img

Dominion’s Chesterfield gas plant could cost ratepayers $4.5B

(The Center Square) – A proposed Dominion Energy gas-fired power plant in Chesterfield County is facing pushback from locals who argue the project could cost ratepayers at least $4.5 billion by 2064.

The project, known as the Chesterfield Energy Reliability Center, was formally submitted to the State Corporation Commission on March 3 as part of Dominion’s request for a certificate of public convenience and necessity. The proposal falls under Rider CERC, a rate adjustment clause allowing the company to recover customer costs over time. Critics argue that this could lock Virginians into decades of higher electricity bills.

The project is currently under review by the State Corporation Commission and is part of Dominion’s plan to expand natural gas generation as Virginia moves toward renewable energy sources.

In testimony before SCC, Dominion Energy witness C. Alan Givens stated that the company calculated rider CERC rates using the same methodology previously approved by the Commission for other rate adjustments.

The process includes forecasting kilowatt-hour (kWh) sales for different customer classes, including residential, business and data centers.

- Advertisement -

According to a recent regulatory filing, the estimate does not include potential increases in fuel costs. Dominion Energy filings show that customers would cover 50% of the project costs while businesses and data centers contribute only 11%.

Dominion Energy confirmed the $4.5 billion cost estimate.

Regarding cost concerns, Dominion told The Center Square in an email that the company estimates that building the plant will cost $1.47 billion and add an average of $1.36 per month to a typical residential customer’s bill over the project’s life. It noted that avoiding reliance on more expensive energy sources from elsewhere will ultimately save customers $1 billion over 30 years.

Due to the massive amounts they consume, data centers in Virginia are projected to be the largest driver of the commonwealth’s energy demand in the future.

“This project would saddle Virginians with a multi-decade financial burden of $4.5 billion—money that could be better invested in cleaner, more affordable energy solutions,” said Glen Besa, Board Chair of Friends of Chesterfield. “This staggering figure exposes the true cost of Dominion’s proposal and confirms that families and businesses will face significantly higher electric bills for decades to come.”

Beyond financial concerns, Virginia’s Clean Energy Act requires utilities to transfer to 100% clean energy by 2045. if approved, customers would be paying for the plant until 2064, two decades beyond Virginia’s renewable energy deadline.

- Advertisement -

The Chesterfield Energy Reliability Center will feature four natural gas-powered turbines capable of generating up to 944 MW, which is enough power for 240,000 homes. Dominion Energy claims the plant will act as an “always ready” backup source, able to start in as little as ten minutes.

The facility will also have a seven-day fuel oil supply and the potential for future hydrogen-blend use.

spot_img
spot_img

Hot this week

Health care company agrees to pay $22.5 million to settle claims of over billing

A health care company agreed to pay nearly $22.5...

Business association ‘disappointed’ by WA L&I’s proposed workers comp rate hike

(The Center Square) – The Association of Washington Business...

Men of Color Expo – Celebrating Men of Excellence

Tinker Federal Credit Union & PPBC Present Men of Color...

Sports betting bill still alive in Georgia House

(The Center Square) – A bill that would allow...

Sports betting expert offers advice on paying taxes for gambling winnings

(The Center Square) – Tax season is underway, and...

Powell out, Warsh in as new chair of Federal Reserve

Kevin Warsh, an economist and former member of the...

Bill to let felons vote from prison draws criticism from Republicans

(The Center Square) – Some Democrats and electoral rights...

Supreme Court yet to decide high profile cases

(The Center Square) — Birthright citizenship, transgender athletes and...

Seattle’s new economic development director wants to end business roadblocks

(The Center Square) - Seattle’s new Economic Development Director...

Gabbard announces resignation, cites personal reasons

Director of National Intelligence Tulsi Gabbard announced her resignation...

Comptroller, Chicago officials debate tax fund sweeps

(The Center Square) – Illinois Comptroller Susana Mendoza and...

WATCH: Christian foster parents win major First Amendment settlement in case against DCYF

(The Center Square) - Washington’s Department of Children, Youth,...

More like this
Related

Powell out, Warsh in as new chair of Federal Reserve

Kevin Warsh, an economist and former member of the...

Bill to let felons vote from prison draws criticism from Republicans

(The Center Square) – Some Democrats and electoral rights...

Supreme Court yet to decide high profile cases

(The Center Square) — Birthright citizenship, transgender athletes and...

Seattle’s new economic development director wants to end business roadblocks

(The Center Square) - Seattle’s new Economic Development Director...