Regulators pause approval of Dominion gas plant

(The Center Square) – Virginia regulators agreed this week to take a second look at their approval of Dominion Energy’s proposed Chesterfield gas plant, temporarily pausing the decision while the project undergoes further review.

In an order issued Tuesday, the Virginia State Corporation Commission granted reconsideration and suspended a Nov. 25 final order tied to the project.

Dominion Energy previously received approval to construct the Chesterfield Energy Reliability Center, a 944-megawatt natural gas plant planned for Chesterfield County. The approval included permission for the utility to recover project costs through a rate adjustment clause known as Rider CERC, which the commission authorized to collect about $35.7 million from customers during the 2026 rate year.

The petition filed with the commission says the approval did not fully comply with requirements under Virginia’s Clean Economy Act and Environmental Justice Act. It also questions whether Dominion demonstrated that the project is necessary to address future electric reliability needs and whether the costs associated with the plant are reasonable for customers.

In granting reconsideration, the commission said it is retaining jurisdiction over the case and suspending execution of its Nov. 25 final order while it considers the petition.

- Advertisement -

Under Virginia law, the State Corporation Commission is responsible for determining whether large energy projects are needed to serve the public before granting approval and allowing utilities to recover costs from ratepayers.

The reconsideration request was filed by the Southern Environmental Law Center on behalf of Appalachian Voices, the Chesterfield NAACP and Mothers Out Front.

In the petition, the groups say the commission did not fully analyze potential health impacts tied to the projected air pollution and relied on limited evidence to justify building new fossil fuel infrastructure. The filing also challenges the commission’s decision to approve cost recovery, citing claims that Dominion has not met certainenergy savings requirements under state law.

“We appreciate the commission’s willingness to take another look at its approval of this unnecessary, dirty, and expensive gas plant,” said Grayson Holmes, a senior attorney with the Southern Environmental Law Center, in a statement following the reconsideration decision.

The commission’s reconsideration order does not set a timeline for when a final decision will be issued. The Nov. 25 order remains suspended while regulators review the petition.

spot_img
spot_img

Hot this week

Health care company agrees to pay $22.5 million to settle claims of over billing

A health care company agreed to pay nearly $22.5...

Business association ‘disappointed’ by WA L&I’s proposed workers comp rate hike

(The Center Square) – The Association of Washington Business...

Men of Color Expo – Celebrating Men of Excellence

Tinker Federal Credit Union & PPBC Present Men of Color...

Sports betting bill still alive in Georgia House

(The Center Square) – A bill that would allow...

Sports betting expert offers advice on paying taxes for gambling winnings

(The Center Square) – Tax season is underway, and...

Supreme Court campaign dispute will extend past the election

(The Center Square) – Miracle Rankin and Jen Auer...

Colo. lawmakers close door on law firms owned by non-attorneys

Colorado lawmakers have overwhelmingly rejected the idea that law...

Procedure changes cause confusion at Caddo Parish School Board

(The Center Square) – The Caddo Parish School Board...

Wisconsin law group receives USDA settlement over race- and sex-based grants

(The Center Square) – The Wisconsin Institute of Law...

War of words reignites with Trump, Pritzker, Bailey

(The Center Square) – President Donald Trump has resumed...

Nesbitt asks DOJ to investigate Whitmer’s ties to grant scandal

Michigan Senate Republican Leader Aric Nesbitt is calling for...

Primaries, Political Power and What Comes Next

WASHINGTON (AURN News) — Primary elections across several states...

More like this
Related

Supreme Court campaign dispute will extend past the election

(The Center Square) – Miracle Rankin and Jen Auer...

Colo. lawmakers close door on law firms owned by non-attorneys

Colorado lawmakers have overwhelmingly rejected the idea that law...

Procedure changes cause confusion at Caddo Parish School Board

(The Center Square) – The Caddo Parish School Board...