California state report: High speed rail faces $6.5 billion funding gap, new delays

The California inspector general tasked with reviewing the state’s high speed rail program issued a new report stating the first segment is likely to be more than three years behind schedule and faces a $6.5 billion funding gap.

“Based on our review of the latest project information, the 2030 target date has been pushed back to 2031, in part because the Authority has extended the timeline for completing construction that is currently underway in the Central Valley,” wrote the Office of the Inspector General in its report. “With a smaller remaining schedule envelope and the potential for significant uncertainty and risk during subsequent phases of the project, staying within the 2033 schedule envelope is unlikely.”

Before the report’s release, Republican Congressman Kevin Kiley had announced a bill to eliminate further federal funding for the project.

The initial 171-mile project will run through the sparsely populated Central Valley and connect the cities of Merced and Bakersfield, with the goal to eventually add spurs to this “backbone” that connect Merced to San Francisco and Bakersfield to Los Angeles.

The first tracks were laid for the project, first approved by voters in 2008, at the start of January, highlighting the system’s lengthy delays.

- Advertisement -

While estimates for the complete statewide project are as high as $135 billion, the inspector’s office noted in an October report that the Merced-Bakersfield segment will likely cost between $32 billion and $35 billion. The California High Speed Rail Authority has expected that it would be able to fill its $6.5 billion funding gap for the initial segment through federal grants, but, as the inspector had noted, and as Republicans have reiterated, that appears unlikely, especially with the current administration.

Hot this week

African and Caribbean Nations Call for Reparations for Slave Trade, Propose Global Fund

Nations across Africa and the Caribbean, deeply impacted by...

Sports betting expert offers advice on paying taxes for gambling winnings

(The Center Square) – Tax season is underway, and...

Health care company agrees to pay $22.5 million to settle claims of over billing

A health care company agreed to pay nearly $22.5...

Entertainment district benefits don’t outweigh the cost, economists say

(The Center Square) — Weeks later, after more details...

Business association ‘disappointed’ by WA L&I’s proposed workers comp rate hike

(The Center Square) – The Association of Washington Business...

Proposed law could allow state agencies to decertify elected sheriffs

(The Center Square) – Voters typically expect higher standards...

Georgia Senate passes sweeping tort reform bill

(The Center Square) – The Georgia Senate passed a...

DOGE subcommittee to hold hearing on USAID spending

Weeks after the nascent Department of Government Efficiency effectively...

Will You Be Getting a Stimulus Check?

(AURN News) — You could possibly receive a stimulus...

Legislation expanding overtime pay protections sent to Youngkin

(The Center Square) – Virginia lawmakers passed two bills...

More like this
Related

Proposed law could allow state agencies to decertify elected sheriffs

(The Center Square) – Voters typically expect higher standards...

Chicago residents express little confidence in CPD, federal reform efforts

(The Center Square) – A new survey finds that...

Georgia Senate passes sweeping tort reform bill

(The Center Square) – The Georgia Senate passed a...

Deportation ad campaign: ‘Leave our country now’ or ‘be hunted down and deported’

(The Center Square) – The U.S. Department of Homeland...