California state report: High speed rail faces $6.5 billion funding gap, new delays

The California inspector general tasked with reviewing the state’s high speed rail program issued a new report stating the first segment is likely to be more than three years behind schedule and faces a $6.5 billion funding gap.

“Based on our review of the latest project information, the 2030 target date has been pushed back to 2031, in part because the Authority has extended the timeline for completing construction that is currently underway in the Central Valley,” wrote the Office of the Inspector General in its report. “With a smaller remaining schedule envelope and the potential for significant uncertainty and risk during subsequent phases of the project, staying within the 2033 schedule envelope is unlikely.”

Before the report’s release, Republican Congressman Kevin Kiley had announced a bill to eliminate further federal funding for the project.

The initial 171-mile project will run through the sparsely populated Central Valley and connect the cities of Merced and Bakersfield, with the goal to eventually add spurs to this “backbone” that connect Merced to San Francisco and Bakersfield to Los Angeles.

The first tracks were laid for the project, first approved by voters in 2008, at the start of January, highlighting the system’s lengthy delays.

- Advertisement -

While estimates for the complete statewide project are as high as $135 billion, the inspector’s office noted in an October report that the Merced-Bakersfield segment will likely cost between $32 billion and $35 billion. The California High Speed Rail Authority has expected that it would be able to fill its $6.5 billion funding gap for the initial segment through federal grants, but, as the inspector had noted, and as Republicans have reiterated, that appears unlikely, especially with the current administration.

spot_img
spot_img

Hot this week

Health care company agrees to pay $22.5 million to settle claims of over billing

A health care company agreed to pay nearly $22.5...

Business association ‘disappointed’ by WA L&I’s proposed workers comp rate hike

(The Center Square) – The Association of Washington Business...

Sports betting bill still alive in Georgia House

(The Center Square) – A bill that would allow...

Sports betting expert offers advice on paying taxes for gambling winnings

(The Center Square) – Tax season is underway, and...

Men of Color Expo – Celebrating Men of Excellence

Tinker Federal Credit Union & PPBC Present Men of Color...

In-state tuition increasing 1% for Georgia’s public colleges

(The Center Square) – Georgia residents attending the state's...

Students in racist chat accuse FIU president of 1A breaches

Four students who took part in a racist group...

Op-Ed: Washington fails the test for affordability

Washington continues to rack up poor rankings as one...

Only major American-owned solar cell maker building in South Carolina

(The Center Square) – Atlanta-based Sunniva announced Tuesday it...

WATCH: Consumer group says higher WA tobacco taxes fueling illegal market

(The Center Square) - Legislation that would have again...

More like this
Related

In-state tuition increasing 1% for Georgia’s public colleges

(The Center Square) – Georgia residents attending the state's...

Students in racist chat accuse FIU president of 1A breaches

Four students who took part in a racist group...

Op-Ed: Washington fails the test for affordability

Washington continues to rack up poor rankings as one...